|  | 
         
          |  |   
          |  |   
          | 8 
            Step Outline for Title 5 Septic Plan: |   
          | Step 
            1  Research Research is done at the Registry of Deeds in Barnstable for 
            applicable deeds and surveyed plot plans.
 
 
 |   
          | Step 
            2  Field 
            Work A survey crew is sent to the property to locate, 
            as necessary, lot boundaries, structures, roadways, topography, existing 
            wells and sewage (on locus and also on abutting properties), wetlands, 
            and other relevant information.
 
 
 |   
          | Step 
            3  Preliminary 
            Draft Once field work is completed, the information 
            will be computed and drafted into a site plan. A suitable location 
            for the Title 5 System is then determined. The client's preference 
            for the location of the system can be implemented if options exist 
            and code requirements can still be met.
 
 
 |   
          | Step 
            4  Percolation 
            and Soil Test With an area for the proposed septic determined, 
            soil testing is required in this location. The soil test consists 
            of digging a minimum of two (2) holes, approximately 10'-15' deep, 
            with either a backhoe or excavator. A soil profile is taken and a 
            percolation test is performed. The results of these tests dictate 
            the type and size of the system. The holes are then filled in and 
            roughly graded over. We are not responsible for returning the grounds 
            to their original condition. If unsuitable soil conditions are found, 
            more testing may be necessary, resulting in additional billing. These 
            third party charges, paid by FELCO, 
            INC., 
            will be billed accordingly as they pertain to your project.
 
 
 |   
          | Step 
            5  Design The system is then designed to meet the proposed 
            or existing dwelling water usage. The site plan with the septic system 
            location, topography, cross-section view of septic components to be 
            used, design calculations, and soil tests are then incorporated into 
            a "Title 5 Site and Sewage Plan".
 
 
 |   
          | Step 
            6  Final 
            Plans A copy of the final plan will be given to the 
            owner for review and comment. Upon receipt of payment, copies of the 
            plan will be distributed to septic system contractors of your choice 
            for bidding purposes. The septic system contractor will submit the 
            Plan to the Board of Health and obtain the installation permit.
 
 
 |   
          | Step 
            7  Construction 
            Phase In many cases it is necessary to stake the 
            locations of the septic components, wells, and foundations on the 
            locus property. FELCO, 
            INC. 
            recommends staking whenever minimum setback distances are critical.
 
 
 |   
          | Step 
            8  Certification Title 
            5 Regulations require the Designer to certify that the septic system 
            was installed in accordance with the approved Septic System Plan. 
            A "Certificate of Compliance Letter" is then sent to the Board of 
            Health certifying the installation. An "As-Built Plan", detailing 
            actual locations, is required in certain towns.
 |  |